ASTON 41 - Site Progress Update



Aston 41 Phase 3 continues to progress on schedule with the completion remaining July 1st 2019.


· The roof cladding is now complete to Unit 3 with the wall cladding well advanced.

· The Steel Frame for Units 4&5 are now complete with the roof cladding well underway.

· Internal fit outs have commenced to Unit 3 with the floor slab fit out scheduled for next week.

· Car parking bays to Unit 3 are currently being constructed and will be ready for tarmac next week.